Predetermined OAR is defined as which of the following?

Prepare for the CIMA BA2 exam with our study guide. Explore multiple choice questions and benefit from expert tips to excel in your test. Get ready to succeed!

Multiple Choice

Predetermined OAR is defined as which of the following?

Explanation:
Predetermined overhead absorption rate is set in advance using budgeted figures: budgeted overhead divided by budgeted activity level. This creates a fixed rate per unit of the chosen cost driver (like hours or machine units) that is used to apply overhead to products during the period. Using budgeted figures keeps the cost per unit stable and enables timely product costing and planning, rather than waiting for actual costs and activity to be known. If you used actual overhead or actual activity, the rate would fluctuate with the period’s performance, leading to over- or under-absorption and less predictable costing.

Predetermined overhead absorption rate is set in advance using budgeted figures: budgeted overhead divided by budgeted activity level. This creates a fixed rate per unit of the chosen cost driver (like hours or machine units) that is used to apply overhead to products during the period. Using budgeted figures keeps the cost per unit stable and enables timely product costing and planning, rather than waiting for actual costs and activity to be known. If you used actual overhead or actual activity, the rate would fluctuate with the period’s performance, leading to over- or under-absorption and less predictable costing.

Subscribe

Get the latest from Examzify

You can unsubscribe at any time. Read our privacy policy